RECENT PROJECTS

  • BRENT HOUSE LONDON HA9

    Brent House
    Brent House
    Brent House
    Brent House

    BRENT HOUSE LONDON HA9

    • Duration: 18 months
    • Type of project: Mixed Use


    QUAD Scaffolding planned and installed access scaffold with 2m fully-board lifts, including loading bays, staircases and hoist towers.


    The existing building was demolished to make way for 248 apartments across six blocks of up to nine storeys. The site includes approximately 16,000 square feet of retail space with a landscaped public plaza in a 1.9 acre site.

  • ARGO HOUSE LONDON SE15

    Argo House
    Argo House
    Argo House
    Argo House

    ARGO HOUSE LONDON SE15

    • Duration 12 months
    • Type of project: Residential + Commercial


    Working in close collaboration with the main contractor, QUAD designed and erected access scaffolds, cantilever loading bays and edge protection.


    Existing buildings were demolished to construct 84 apartments in three blocks of five, eight and nine storeys, with flexible ground floor working spaces.

  • BARNES VILLAGE CHEADLE SK8

    Barnes Village
    Barnes Village
    Barnes Village
    Barnes Village
    Barnes Village
    Barnes Village
    Barnes Village
    Barnes Village

    BARNES VILLAGE CHEADLE SK8

    • Duration 24 months
    • Type of project: Residential + Listed Building Conversion


    We provided access scaffolding in 2m fully-boarded lifts with loading bays, hoist towers and staircases


    Conversion of a large listed Victorian hospital Set in 16.5 acres of landscaped grounds, this landmark project provided 117 new-build family homes and involved re-glazing, façade cleaning and repair of the original structure, replacement of the slate roof and the restoration of a circa 30 metre clock tower.

  • 67-68 Pall Mall LONDON SW1

    Pall Mall
    Pall Mall

    67-68 Pall Mall LONDON SW1

    • Duration: 14 weeks
    • Type of project: Renovation


    QUAD Scaffolding provided 2m fully-boarded lifts, scaffold gantry, chimney stack and roof edge protection guardrails.


    Three facades of a private members’ club cleaned using the DOFF steam system in an iconic Lutyens Building on Pall Mall.

  • lampton road Hounslow TW3

    Lampton Road
    Lampton Road
    Lampton Road
    Lampton Road

    lampton road Hounslow TW3

    • Duration 12 months
    • Type of project: Residential


    QUAD Scaffolding designed, specified and erected 2m fully-boarded lifts, scaffold gantry, chimney stack and roof edge protection guardrails


    Lampton Road is a 98 new-build home development.

  • Great Titchfield Street London W1

    Great Titchfield Street London W1

    • Duration 18 months
    • Type of project: Commercial


    We installed temporary roof covers and lift shaft scaffolds to riser shafts, stairways and hanging scaffolds in one of London’s busiest locations. QUAD worked closely with the main contractor to address all scaffolding requirements.